Shepherd Park Community Center Update – May 23

Prepared on: May 23, 2018
Location: 7800 14th Street, NW, Washington, DC 20012
Ward: 4
Feasibility Study Architect: dp+partners
Design Builder/Architects: TBD
Project Budget: $13.1M
Project Status: Kick Off/Feasibility Study

DCPS Project Website

DPR/DGS Project Website

General Project Overview

DCPS is working in conjunction with DPR for a new Shepherd Park Community Center which will
connect directly to the elementary school building. This addition will include a gymnasium,
kitchen, fitness room and multipurpose classroom spaces. Final scope of project dependent
upon results of feasibility study and community input.

Project Status

Summary of Work Completed over the Past Month

  • dp+partners is finalizing their feasibility study, gearing up to submit final results.
  • DPR, DGS, and DCPS met with Principal Brawley to fully understand school needs in conjunction with the project.

Next steps from May 28 – June 08

DGS, DPR, and DCPS will work on drafting a RFP for a Design/Build team based
on the feasibility study results.

Community Outreach Update

DPR hosted a Community Meeting at Shepherd Elementary on April 17 to introduce the
feasibility study and get input from the community.

Project Contacts

Please reach out to Charlotte Boyer with any questions or concerns about the project as it relates to Shepherd Elementary or Brent Sisco for questions or concerns on the project as a whole.

Thank you for your support of the project!